# James Construction Group, LLC: TxDOT miscellaneous construction contract 97% complete, FM 1764, Galveston County ($18,055,749, 15 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Williams Road, LLC (0.92%); Primate Construction, LP (0.47%); Highway 1 LLC (0%); Cherry Moving Company, INC. (1.2%); Aviles Construction Service, INC (2.04%); Who-B Trucking, INC. (0.5%); Traffic Signs & Lines, LLC (3.5%); Texas Materials Group, INC. (26.44%); Cpave, INC. (0.11%); Trp Construction Group, LLC (0.22%); Curb Planet INC. (0.07%); Traffic Systems Construction, INC. (1.07%); Quality Turf Farms, L.C. (0.23%); Hermanos Steel, LLC (4.01%); Romar Unlimited, INC. (0.25%) |
| Progress | 96.83% complete, 100% of time used |
| Amount | $18,055,749 revised (original $17,513,705) |
| Change orders | $12,043 |
| Paid to date | $16,971,050 |
| Work | Miscellaneous Construction |
| Location | FM 1764, W OF SH 3 to 14TH STREET, Galveston County, Houston District |
| Let / began | 2024-09-06 / 2025-02-03 |
| Latest estimate | 2026-09-30 |
| Contract number | 9243207 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.