# James Hamilton Construction Co.: TxDOT restoration contract 80% complete, SH 214, Cochran County ($34,968,093, 11 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | James Hamilton Construction Co. |
| Subcontractors | Professional Traffic Control LLC (0.1%); Nm Ac & Company LLC (2.1%); Murray Construction (0.32%); Fc Traffic Control, INC. (0.18%); Square Root Services LLC (0.05%); Cm Company (0.03%); W. S. Construction Company (1.1%); Industrial Fabrics, INC. (7.61%); Trp Construction Group, LLC (1.39%); Texas Environmental Management - San Antonio, INC. (0.33%); Apollo Constructors, INC. (0.05%) |
| Progress | 79.91% complete, 95.36% of time used |
| Amount | $34,968,093 revised (original $28,894,124) |
| Change orders | $4,465,595 |
| Paid to date | $26,659,095 |
| Work | Restoration |
| Location | SH 214, MORTON to YOAKUM, Cochran County, Lubbock District |
| Let / began | 2025-01-08 / 2025-05-12 |
| Latest estimate | 2026-10-06 |
| Contract number | 1253204 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.