# James Hamilton Construction Co.: TxDOT rehabilitation of existing road contract 100%+ complete, RM 652, Culberson County ($30,058,509, 13 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | James Hamilton Construction Co. |
| Subcontractors | A Brothers Milling, LLC (1.03%); Hjc Farms, INC. (0.66%); Professional Traffic Control LLC (0.07%); Square Root Services LLC (0.56%); Titan Milling INC. (0.35%); Tri State Electric, LTD. (0.88%); Trp Construction Group, LLC (1.4%); Dk Contracting, LLC (0.29%); Fc Traffic Control, INC. (0.19%); Barnhart Crane & Rigging Company (0.04%); Nm Ac & Company LLC (3.68%); West Texas Rumble Strip LLC (0.17%); Built Concrete Construction, LLC (1.51%) |
| Progress | 100.66% complete, 98.5% of time used |
| Amount | $30,058,509 revised (original $29,265,512) |
| Change orders | $151,097 |
| Paid to date | $29,611,768 |
| Work | Rehabilitation Of Existing Road |
| Location | RM 652, FM 1108 INTERSECTION to 0.17 MI E OF FM 1108, Culberson County, El Paso District |
| Let / began | 2024-05-02 / 2024-08-12 |
| Latest estimate | 2026-10-05 |
| Contract number | 5243006 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.