# Jcw Construction, LLC: TxDOT maintenance contract 100%+ complete, US0059, Wharton County ($2,436,333)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Jcw Construction, LLC |
| Progress | 113.16% complete, 100% of time used |
| Amount | $2,436,333 revised (original $1,041,864) |
| Change orders | $1,394,466 |
| Paid to date | $2,757,025 |
| Work | Maintenance |
| Location | US0059, WHARTON, MATAGORDA, AND AUSTIN COUNTIES to ., Wharton County, Yoakum District |
| Let / began | 2022-04-06 / 2022-09-06 |
| Latest estimate | 2026-10-05 |
| Contract number | 4224019 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.