# Joe Bland Construction LLC: TxDOT rehabilitation of existing road contract 33% complete, US 183, Williamson County ($14,881,672, 7 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Joe Bland Construction LLC |
| Subcontractors | Buyers Barricades Austin, LLC (0.43%); *austin Traffic Signal Construction Co., INC. (0.17%); Lone Star Paving Company (41.91%); The Davey Tree Expert Company (0.06%); D. I. J. Construction, INC. (1.44%); Environmental Safety Services, INC. (9.02%); Tor Texas, LLC (0.4%) |
| Progress | 32.63% complete, 45.7% of time used |
| Amount | $14,881,672 revised (original $14,639,581) |
| Change orders | $7,089 |
| Paid to date | $4,778,668 |
| Work | Rehabilitation Of Existing Road |
| Location | US 183, SH 138 to 0.23 MILES N. OF CR 254, Williamson County, Austin District |
| Let / began | 2025-11-05 / 2026-01-30 |
| Latest estimate | 2026-10-05 |
| Contract number | 11253005 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.