# Johnson Bros. Corporation, A Southland Company: TxDOT rehabilitation of existing road contract 92% complete, US 175, Dallas County ($81,724,577, 28 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Johnson Bros. Corporation, A Southland Company |
| Subcontractors | Elite Emerald Construction, LLC (0.09%); Rangeline Utility Services LLC DBA Ruts Construction (0.24%); Oscar Renda Contracting, INC. (3.12%); Monarrez Trucking LLC. (0.25%); Traffic Tech Solutions, LLC (0.17%); Austin Bridge & Road Services, LP (0.11%); A&E Sealing Texas (0.09%); Rey-Mar Construction (1.65%); Integrated Roadway Services, INC. (5.61%); Striping Technology, L.P. (0.55%); Texas Utility Services LLC (3.15%); Area Wide Protective, INC. (0.13%); Heritage Materials, LLC (1.5%); Penhall Company (0.03%); Lindamood Demolition, INC. (1.28%); Oscar Orduno, INC. (1.14%); Act Saw Cutting & Removal (0.1%); Ancortex, INC. (0%); Jb Pinnacle Group, LLC (3.83%); Straight Line Sawing & Sealing, INC. (0.01%); Toro Bravo Construction, LLC (0.08%); Massey Contractors, LLC (0.16%); Q. Roberts Trucking Incorporated (1%); D. T. Read Steel Co., INC. (0.21%); Lindamood, INC. (0%); Texas Environmental Management - San Antonio, INC. (2.16%); Coronado R. Construction, LLC (0.04%); J.H. Painting Company (0.2%) |
| Progress | 92.22% complete, 206.33% of time used |
| Amount | $81,724,577 revised (original $78,665,971) |
| Change orders | $1,561,196 |
| Paid to date | $73,989,022 |
| Work | Rehabilitation Of Existing Road |
| Location | US 175, SOUTH OF BUDD ST to IH 45, Dallas County, Dallas District |
| Let / began | 2019-12-03 / 2020-07-06 |
| Latest estimate | 2026-10-02 |
| Contract number | 12193001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.