# Jones Bros. Dirt & Paving Contractors, INC.: TxDOT widen non-freeway contract 16% complete, US 67, Upton County ($27,335,957, 12 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Jones Bros. Dirt & Paving Contractors, INC. |
| Subcontractors | Trp Construction Group, LLC (2.6%); Texas Environmental Management - San Antonio, INC. (0.44%); Hjc Farms, INC. (1.08%); Contractors Service, LTD. (0.48%); Double A Contracting, L.P. (0.09%); Relmco, INC. (31.57%); Performance Equipment Service (1.03%); Long Legacy Enterprises, LLC (0.4%); R.E.B.D. Trucking LLC (0%); Willis Electric Co., LP (2.44%); Marcoms Construction LLC (0.53%); Toro Bravo Construction, LLC (0.12%) |
| Progress | 16.36% complete, 17.36% of time used |
| Amount | $27,335,957 revised (original $25,682,913) |
| Change orders | $633,354 |
| Paid to date | $4,306,248 |
| Work | Widen Non-Freeway |
| Location | US 67, REAGAN COUNTY LINE to SH 329, Upton County, Odessa District |
| Let / began | 2025-10-08 / 2026-03-19 |
| Latest estimate | 2026-09-30 |
| Contract number | 10253002 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.