# Jones Bros. Dirt & Paving Contractors, INC.: TxDOT widen freeway contract 11% complete, SH 115, Winkler County ($25,593,201, 9 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Jones Bros. Dirt & Paving Contractors, INC. |
| Subcontractors | Contractors Service, LTD. (0.55%); W. S. Construction Company (14.05%); Texop Construction (1.34%); Willis Electric Co., LP (1.34%); R.E.B.D. Trucking LLC (0%); Texas Environmental Management - San Antonio, INC. (0.4%); Hjc Farms, INC. (0.82%); Double A Contracting, L.P. (4.41%); Dk Contracting, LLC (0.3%) |
| Progress | 11.28% complete, 20.28% of time used |
| Amount | $25,593,201 revised (original $24,397,885) |
| Paid to date | $2,751,151 |
| Work | Widen Freeway |
| Location | SH 115, 3 MI S OF ANDREWS COUNTY LINE to SH 128, Winkler County, Odessa District |
| Let / began | 2025-12-02 / 2026-05-20 |
| Latest estimate | 2026-10-01 |
| Contract number | 12253002 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.