# Jones Bros. Dirt & Paving Contractors, INC.: TxDOT widen freeway contract 20% complete, US 285, Pecos County ($27,673,482, 10 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Jones Bros. Dirt & Paving Contractors, INC. |
| Subcontractors | Relmco, INC. (24.03%); R.E.B.D. Trucking LLC (0%); Double A Contracting, L.P. (4.14%); Texas Environmental Management - San Antonio, INC. (0.67%); Contractors Service, LTD. (0.73%); Hjc Farms, INC. (0.61%); Texop Construction (0.97%); Willis Electric Co., LP (0.43%); Dk Contracting, LLC (0.41%); Long Legacy Enterprises, LLC (0.39%) |
| Progress | 20.15% complete, 38.36% of time used |
| Amount | $27,673,482 revised (original $26,858,499) |
| Paid to date | $5,411,882 |
| Work | Widen Freeway |
| Location | US 285, 0.7 MI NORTH OF W GOMEZ RD to 1.8 MI NORTH OF IH 10, Pecos County, Odessa District |
| Let / began | 2025-04-03 / 2025-12-01 |
| Latest estimate | 2026-09-30 |
| Contract number | 4253002 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.