# Jones Bros. Dirt & Paving Contractors, INC.: TxDOT rehabilitation of existing road contract 100%+ complete, US 67, Pecos County ($41,634,268, 11 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Jones Bros. Dirt & Paving Contractors, INC. |
| Subcontractors | Altex Landscape Construction, INC. (0.12%); R.E.B.D. Trucking LLC (0%); Double A Contracting, L.P. (0.03%); Contractors Service, LTD. (0.42%); Hjc Farms, INC. (2.26%); Dustrol, INC. (0.82%); Cox Paving Company Of Texas, INC. (22.82%); Marcom's Mowing Service, LLC (0.25%); Relmco, INC. (2.43%); Stripe-A-Zone, LLC (0.16%); Farr Foundation, INC. (0.32%) |
| Progress | 114.99% complete, 101.91% of time used |
| Amount | $41,634,268 revised (original $35,754,470) |
| Change orders | $4,582,175 |
| Paid to date | $46,384,727 |
| Work | Rehabilitation Of Existing Road |
| Location | US 67, 16.8 m S of IH 10 to Brewster C/L, Pecos County, Odessa District |
| Let / began | 2021-06-04 / 2021-11-01 |
| Latest estimate | 2026-09-30 |
| Contract number | 6213204 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.