# Jones Bros. Dirt & Paving Contractors, INC.: TxDOT bridge replacement contract 96% complete, US 285, Reeves County ($48,250,918, 14 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Jones Bros. Dirt & Paving Contractors, INC. |
| Subcontractors | Fibertex, LLC (0.03%); Coppell Construction Co., INC. (7.07%); Desert Paving, INC. (0.46%); J. H. Oden Contracting Company (1.06%); Penhall Company (0.03%); Hermanos Steel, LLC (0.04%); Double A Contracting, L.P. (0.65%); Highway Pavement Specialties, INC. (0.01%); Texas Shafts, INC. (0.89%); Relmco, INC. (11.16%); Hjc Farms, INC. (2.56%); R.E.B.D. Trucking LLC (4.24%); Texop Construction (0.52%); Willis Electric Co., LP (0.56%) |
| Progress | 96.34% complete, 99.85% of time used |
| Amount | $48,250,918 revised (original $46,043,243) |
| Change orders | $1,061,082 |
| Paid to date | $45,380,708 |
| Work | Bridge Replacement |
| Location | US 285, from RM 652 to CR 232 (& at Four Mile Draw), Reeves County, Odessa District |
| Let / began | 2022-06-29 / 2023-03-06 |
| Latest estimate | 2026-09-30 |
| Contract number | 6223403 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.