# Jones Bros. Dirt & Paving Contractors, INC.: TxDOT rehabilitation of existing road contract 100%+ complete, IH 20, Martin County ($12,121,541, 7 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Jones Bros. Dirt & Paving Contractors, INC. |
| Subcontractors | Contractors Service, LTD. (0.37%); Desert Paving, INC. (0.42%); Dk Contracting, LLC (0.5%); Double A Contracting, L.P. (0.5%); J. H. Oden Contracting Company (0.21%); Texop Construction (1.92%); R.E.B.D. Trucking LLC (1.32%) |
| Progress | 105.09% complete, 77.09% of time used |
| Amount | $12,121,541 revised (original $11,318,569) |
| Change orders | $96,197 |
| Paid to date | $11,996,195 |
| Work | Rehabilitation Of Existing Road |
| Location | IH 20, STANTON (EAST INTERCHANGE) to HOWARD COUNTY LINE, Martin County, Odessa District |
| Let / began | 2025-06-05 / 2025-12-01 |
| Latest estimate | 2026-09-30 |
| Contract number | 6253203 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.