# Jones Bros. Dirt & Paving Contractors, INC.: TxDOT overlay contract 100%+ complete, SH 349, Midland County ($8,686,228, 6 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Jones Bros. Dirt & Paving Contractors, INC. |
| Subcontractors | Double A Contracting, L.P. (2.67%); Performance Equipment Service (1.03%); Wims Environmental Construction, LTD. (0.12%); R.E.B.D. Trucking LLC (0.01%); Dk Contracting, LLC (0.97%); Contractors Service, LTD. (0.68%) |
| Progress | 103.95% complete, 69.92% of time used |
| Amount | $8,686,228 revised (original $5,391,295) |
| Change orders | $2,865,689 |
| Paid to date | $8,583,248 |
| Work | Overlay |
| Location | SH 349, IH 20 S FRONTAGE RD - SH 191 to 3 MI S OF IH 20 S FRONTAGE RD, Midland County, Odessa District |
| Let / began | 2025-09-05 / 2026-03-23 |
| Latest estimate | 2026-09-30 |
| Contract number | 9253212 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.