# Jordan Foster Construction, LLC: TxDOT miscellaneous construction contract 90% complete, US 62, El Paso County ($272,196,819, 24 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Jordan Foster Construction, LLC |
| Subcontractors | A Brothers Milling, LLC (0.1%); Pavement Markings INC. (0.37%); Traffic Barricade Service, INC. (0.13%); Sanchez Construction & Landscaping (0.27%); Border Demolition And Environmental, INC. (0.13%); Hawk Construction (2.39%); Damcon (0.99%); Ztex Construction, INC. (3.55%); Tri State Electric, LTD. (6.15%); F A L C Enterprises, LLC. (0.24%); Crane Services, INC. (0.16%); Hdw Construction & Drilling, LLC. (0.37%); Garcom, INC. (0.17%); Apollo Constructors, INC. (0.01%); Major Motion Logistics, LLC (0.01%); Tpg Pressure, INC. (0%); Texas Far West Construction & Engineering (0%); Border Drilling LLC (0.06%); Pmi Pavement Marking, LLC (0.37%); Thorcon Shotcrete And Shoring LLC (4.36%); Penhall Company (0.12%); Tfw C&E, LLC (0%); 915 Accurate Coring LLC (0%); Ctxep Specialty Services (0%) |
| Progress | 90.48% complete, 93.68% of time used |
| Amount | $272,196,819 revised (original $144,207,911) |
| Change orders | $126,931,486 |
| Paid to date | $245,322,198 |
| Work | Miscellaneous Construction |
| Location | US 62, GLOBAL REACH DR to FM 659 (ZARAGOZA RD), El Paso County, El Paso District |
| Let / began | 2018-10-03 / 2019-04-22 |
| Latest estimate | 2026-10-02 |
| Contract number | 10183227 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.