# Jordan Foster Construction, LLC: TxDOT widen freeway contract 85% complete, SL 375, El Paso County ($145,348,189, 24 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Jordan Foster Construction, LLC |
| Subcontractors | Oscar Orduno, INC. (0.39%); A Brothers Milling, LLC (0.21%); Traffic Barricade Service, INC. (0.49%); Hawk Construction (2.32%); Sanchez Construction & Landscaping (0.46%); Ztex Construction, INC. (3.6%); Tri State Electric, LTD. (9.04%); S.J. Louis Construction, INC. (16.56%); Pmi Pavement Marking, LLC (0.49%); Ctc Innovations, LLC (0.12%); Major Motion Logistics, LLC (0.15%); Scott Derr Painting Co, LLC (0.15%); Border Demolition And Environmental, INC. (0.13%); Surface Preparation Technologies, LLC (0.01%); Satarain Construction, INC. (0.93%); North Star Trenchless LLC (5.19%); Tda, INC. (0.58%); Apex Contracting Enterprises, LLC. (0.68%); Damcon (0.09%); Je Casey, LLC (0.23%); Border Drilling LLC (0%); Crane Services, INC. (0.09%); Penhall Company (0.01%); Organ Mountain Site Solutions LLC (0.01%) |
| Progress | 85.17% complete, 97.73% of time used |
| Amount | $145,348,189 revised (original $137,955,531) |
| Change orders | $4,631,803 |
| Paid to date | $121,435,019 |
| Work | Widen Freeway |
| Location | SL 375, SPUR 601 to MONTANA AVE (US 62/180), El Paso County, El Paso District |
| Let / began | 2022-05-04 / 2022-09-12 |
| Latest estimate | 2026-10-02 |
| Contract number | 5223002 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.