# Jordan Foster Construction, LLC: TxDOT rehabilitation of existing road contract 73% complete, FM 1281, El Paso County ($39,552,362, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Jordan Foster Construction, LLC |
| Subcontractors | Border Drilling LLC (0.19%); Major Motion Logistics, LLC (0.3%); Pmi Pavement Marking, LLC (1.1%); Satarain Construction, INC. (6.24%); A Brothers Milling, LLC (0.37%); Border Demolition And Environmental, INC. (1.72%); Traffic Barricade Service, INC. (1.61%); Tri State Electric, LTD. (11.18%); Ztex Construction, INC. (6.12%); Ctc Innovations, LLC (0.3%); Apex Contracting Enterprises, LLC. (0.74%); Sanchez Construction & Landscaping (1.9%); El Paso J.A.G., INC. (0.06%); Accurate Electric And Solar LLC (0.01%) |
| Progress | 73.29% complete, 86.2% of time used |
| Amount | $39,552,362 revised (original $36,413,140) |
| Change orders | $658,551 |
| Paid to date | $27,170,250 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 1281, HORIZON BLVD AT DARRINGTON INTERSEC to ., El Paso County, El Paso District |
| Let / began | 2023-06-27 / 2024-01-08 |
| Latest estimate | 2026-10-02 |
| Contract number | 6233407 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.