# Jordan Foster Construction, LLC: TxDOT convert non-freeway to freeway contract 37% complete, US 90, Bexar County ($124,809,706, 20 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Jordan Foster Construction, LLC |
| Subcontractors | Z & L Concrete Contractors, INC. (2.07%); J. R. (Joe) Ramon & Sons, INC. (0.14%); Sk Concrete Services LLC (0.05%); (Inactive)stripe It Up, LLC (1.15%); Choctaw Erectors, INC. (0.3%); Dc Civil Construction, LLC (0.18%); Lone Star Paving Company (16.38%); Taylor Contracting LLC (1.21%); Royal Rebar INC (0.68%); Aaron Concrete Contractors, LLC (1.26%); Freyssinet, INC. (0.06%); Beaird Drilling Services, INC. (2.71%); Flasher Equipment Company (0.17%); Eggemeyer Land Clearing, LLC (0.06%); Scott Derr Painting Co, LLC (0.22%); Performance Equipment Service (0.94%); Badeco, INC. (0.02%); The Levy Company, LLC (4.52%); Fibertel, LLC (0.51%); A K Fuquay Construction (0%) |
| Progress | 36.55% complete, 19.88% of time used |
| Amount | $124,809,706 revised (original $123,992,266) |
| Change orders | $817,440 |
| Paid to date | $45,613,942 |
| Work | Convert Non-Freeway To Freeway |
| Location | US 90, SH 211 to 0.8 MILES W OF IH 410, Bexar County, San Antonio District |
| Let / began | 2025-06-05 / 2025-10-27 |
| Latest estimate | 2026-10-05 |
| Contract number | 6253201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.