# Jordan Foster Construction, LLC: TxDOT interchange (new or reconstructed) contract 39% complete, SL 375, El Paso County ($12,876,264, 6 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Jordan Foster Construction, LLC |
| Subcontractors | Border Demolition And Environmental, INC. (4.57%); Traffic Barricade Service, INC. (1.51%); Hawk Construction (6.96%); Tri State Electric, LTD. (6.48%); Damcon (6.72%); Satarain Construction, INC. (6.04%) |
| Progress | 39.13% complete, 55.13% of time used |
| Amount | $12,876,264 revised (original $11,897,786) |
| Change orders | $678,478 |
| Paid to date | $4,920,942 |
| Work | Interchange (New Or Reconstructed) |
| Location | SL 375, LOOP 375 to SERGEANT MAJOR BOULEVARD, El Paso County, El Paso District |
| Let / began | 2025-07-02 / 2026-01-12 |
| Latest estimate | 2026-10-02 |
| Contract number | 7253205 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.