# Jordan Foster Construction, LLC: TxDOT widen freeway contract 100%+ complete, IH 10, Bexar County ($100,848,461, 21 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Jordan Foster Construction, LLC |
| Subcontractors | Trp Construction Group, LLC (0.61%); Buyers Barricades San Antonio, LLC (0.52%); F & W Electrical Contractors, INC. (2.37%); Texas Environmental Management - San Antonio, INC. (0.49%); Toro Bravo Construction, LLC (1.15%); Penhall Company (0.01%); (Inactive)aaron Concrete Contractors, L.P. (1.14%); Texas Materials Group, INC. (10.52%); Roadway Specialties, INC. (0.47%); Adcock 4 Investments, LLC (1.76%); J. R. (Joe) Ramon & Sons, INC. (0.18%); Bexar Concrete Works Incorporated (4.81%); Light It Up Electric (0.21%); Ancortex, INC. (1.45%); Roadway Construction, INC. (2.82%); (Inactive)beaird Drilling (1.5%); K. L. Durham Construction, L.L.C. (0.49%); (Inactive)royal Rebar (0.15%); Aaron Concrete Contractors, LLC (1.14%); Sk Concrete Services LLC (0.15%); A-Core Concrete Cutting Of Texas, INC. (0.06%) |
| Progress | 105.99% complete, 99.94% of time used |
| Amount | $100,848,461 revised (original $91,651,868) |
| Change orders | $9,196,593 |
| Paid to date | $106,889,101 |
| Work | Widen Freeway |
| Location | IH 10, LOOP 1604 to GRAYTOWN RD, Bexar County, San Antonio District |
| Let / began | 2019-08-07 / 2020-02-03 |
| Latest estimate | 2026-10-06 |
| Contract number | 8193202 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.