# Jordan Foster Construction, LLC: TxDOT widen non-freeway contract 68% complete, FM 1516, Bexar County ($70,854,434, 13 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Jordan Foster Construction, LLC |
| Subcontractors | (Inactive)beaird Drilling (0.87%); Benton-Georgia, LLC (2.31%); Texas Materials Group, INC. (13.26%); Dc Civil Construction, LLC (11.35%); A K Fuquay Construction (0.56%); Eggemeyer Land Clearing, LLC (0.13%); Roadway Specialties, INC. (0.26%); Trp Construction Group, LLC (0.94%); A Brothers Milling, LLC (0.51%); D&G Energy Corporation (2.23%); S&S Bridge Painting (0.08%); Z & L Concrete Contractors, INC. (4.44%); C&M Precast Concrete Company (2.61%) |
| Progress | 68.33% complete, 60.74% of time used |
| Amount | $70,854,434 revised (original $68,941,542) |
| Change orders | $1,912,892 |
| Paid to date | $48,413,090 |
| Work | Widen Non-Freeway |
| Location | FM 1516, FM 78 to IH 10, Bexar County, San Antonio District |
| Let / began | 2023-08-02 / 2024-01-03 |
| Latest estimate | 2026-10-06 |
| Contract number | 8233002 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.