# Kiewit Infrastructure South Co.: TxDOT overlay contract 100%+ complete, IH 10, Crockett County ($23,700,583, 11 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Kiewit Infrastructure South Co. |
| Subcontractors | J H Trucking (7.51%); T. Davis Transport LLC (13.06%); Professional Traffic Control LLC (0.16%); Hjc Farms, INC. (7.64%); Fc Traffic Control, INC. (0.25%); Trp Construction Group, LLC (2.45%); Mobile Enterprises, INC. (0.31%); W. S. Construction Company (2.45%); Jvh4 Services, LLC (0.01%); Hudson, INC. South (1.15%); Allen Keller Company (1.06%) |
| Progress | 101.71% complete, 66.05% of time used |
| Amount | $23,700,583 revised (original $24,564,337) |
| Change orders | $-1,711,155 |
| Paid to date | $23,244,641 |
| Work | Overlay |
| Location | IH 10, PECOS COUNTY LINE to 15.9 MI EAST OF PECOS COUNTY LINE, Crockett County, San Angelo District |
| Let / began | 2025-02-06 / 2025-08-04 |
| Latest estimate | 2026-10-06 |
| Contract number | 2253002 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.