# Knife River Corporation - South: TxDOT rehabilitation of existing road contract 97% complete, FM 2780, Washington County ($17,619,876, 12 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Knife River Corporation - South |
| Subcontractors | Brock Construction, LLC (0.14%); Batten Drilling, INC. (0.9%); Trp Construction Group, LLC (0.21%); Scr Civil Construction, LLC (0.13%); Cen Tex Hydroseed, INC. (1.26%); Traffic Signs & Lines, LLC (1.46%); Cen-Tree Solutions LLC (0.79%); D. I. J. Construction, INC. (1.18%); Kingz Industrial LLC (1.77%); J. H. Oden Contracting Company (0.18%); Highway 1 LLC (0.21%); Third Coast Services LLC (0.25%) |
| Progress | 97.1% complete, 104.78% of time used |
| Amount | $17,619,876 revised (original $17,441,399) |
| Paid to date | $16,936,352 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 2780, FM 1697 NORTH to FM 1697 SOUTH, Washington County, Bryan District |
| Let / began | 2024-10-01 / 2025-03-03 |
| Latest estimate | 2026-09-29 |
| Contract number | 10243007 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.