# Knife River Corporation - South: TxDOT bridge replacement contract 67% complete, SH 220, Erath County ($10,068,472, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Knife River Corporation - South |
| Subcontractors | Cnd Contracting, LLC (0.27%); Lindamood, INC. (1.2%); Primate Construction, LP (0.2%); Jb Pinnacle Group, LLC (2.19%); Diibs Specialists, LLC (0.75%); Trp Construction Group, LLC (0.97%); Highway Traffic Control & Services, LLC (1.04%); Cen-Tree Solutions LLC (0.5%); Texas Environmental Management - San Antonio, INC. (2.38%); Texas Shafts, INC. (2.66%); Hermanos Steel, LLC (2.56%); Tex Op Construction, LP (0.08%); Wilko Industrial, L.L.C. (0.11%); West Texas Rumble Strip LLC (0.08%) |
| Progress | 66.94% complete, 74.22% of time used |
| Amount | $10,068,472 revised (original $9,849,855) |
| Change orders | $14,117 |
| Paid to date | $6,603,059 |
| Work | Bridge Replacement |
| Location | SH 220, AT LITTLE DUFFAU CREEK to ., Erath County, Fort Worth District |
| Let / began | 2024-10-02 / 2025-03-03 |
| Latest estimate | 2026-10-02 |
| Contract number | 10243229 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.