# Knife River Corporation - South: TxDOT rehabilitation of existing road contract 87% complete, SS 579, Hill County ($3,612,413, 8 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Knife River Corporation - South |
| Subcontractors | West Texas Rumble Strip LLC (0.2%); O. Trevino Construction, LLC (16.72%); Trp Construction Group, LLC (1.58%); *austin Traffic Signal Construction Co., INC. (0.5%); Bear Creek Construction, LLC (4.81%); Highway Traffic Control & Services, LLC (1.06%); Cox Paving Of Texas, INC. (9.92%); Cen Tex Hydroseed, INC. (0.19%) |
| Progress | 86.84% complete, 82.96% of time used |
| Amount | $3,612,413 revised (original $3,553,261) |
| Change orders | $59,152 |
| Paid to date | $3,137,044 |
| Work | Rehabilitation Of Existing Road |
| Location | SS 579, IH 35 to 1.02 MI W OF IH 35, Hill County, Waco District |
| Let / began | 2025-10-08 / 2026-02-17 |
| Latest estimate | 2026-10-02 |
| Contract number | 10253031 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.