# Knife River Corporation - South: TxDOT restoration contract 95% complete, FM 879, Ellis County ($9,430,548, 10 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Knife River Corporation - South |
| Subcontractors | A. E. Moore Construction, INC. (0%); Bear Creek Construction, LLC (0%); Civil Tree Solutions, LLC (0%); Fortson Contracting, INC. (0%); Highway Traffic Control & Services, LLC (0%); Texas Traffic And Barricade, LLC (0%); Professional Traffic Control LLC (0%); Traffic Highway Maintenance, LLC (0%); (Inactive)site Barricades (0.37%); Site Partners, LLC (0.37%) |
| Progress | 94.7% complete, 89.89% of time used |
| Amount | $9,430,548 revised (original $9,167,314) |
| Change orders | $177,234 |
| Paid to date | $8,848,849 |
| Work | Restoration |
| Location | FM 879, 0.3 MILES WEST OF FM 1722 to FM 813, Ellis County, Dallas District |
| Let / began | 2025-03-04 / 2025-07-07 |
| Latest estimate | 2026-10-05 |
| Contract number | 3253008 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.