# Knife River Corporation - South: TxDOT overlay contract 97% complete, FM 1887, Waller County ($1,082,940, 2 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Knife River Corporation - South |
| Subcontractors | Stripe Lines, INC. (3.55%); West Texas Rumble Strip LLC (0.73%) |
| Progress | 97.33% complete, 60% of time used |
| Amount | $1,082,940 revised (original $1,140,623) |
| Change orders | $-94,683 |
| Paid to date | $1,018,040 |
| Work | Overlay |
| Location | FM 1887, SH 159 to FM 359, Waller County, Houston District |
| Let / began | 2026-04-08 / 2026-06-26 |
| Latest estimate | 2026-09-30 |
| Contract number | 4263220 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.