# Knife River Corporation - South: TxDOT rehabilitation of existing road contract 55% complete, FM 2293, Robertson County ($18,550,009, 18 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Knife River Corporation - South |
| Subcontractors | Wilko Industrial, L.L.C. (2.02%); Jb Pinnacle Group, LLC (0.5%); Scott Derr Painting Co, LLC (0.03%); Sk Concrete Services LLC (0.04%); Cnd Contracting, LLC (0.32%); Highway Traffic Control & Services, LLC (0.65%); J & M Contracting, Company (2.63%); Cen Tex Hydroseed, INC. (2.36%); Cen-Tree Solutions LLC (1.02%); Striping Technology, L.P. (2.07%); *austin Traffic Signal Construction Co., INC. (0.09%); Bear Creek Construction, LLC (9.41%); Civil Tree Solutions, LLC (0.08%); Fortson Contracting, INC. (0.86%); Gk Construction, LLC (0.05%); M & D Foundation Drilling Industries, INC. (1.07%); (Inactive)hogan Murray, INC. (0%); Murray Construction (0%) |
| Progress | 55.09% complete, 44.14% of time used |
| Amount | $18,550,009 revised (original $18,180,795) |
| Paid to date | $10,015,097 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 2293, FM 46 to FM 979, Robertson County, Bryan District |
| Let / began | 2025-07-02 / 2025-11-05 |
| Latest estimate | 2026-09-29 |
| Contract number | 7253206 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.