# Knife River Corporation - South: TxDOT hazard elimination & safety contract 96% complete, FM 2377, Ellis County ($6,786,052, 12 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Knife River Corporation - South |
| Subcontractors | Traffic Highway Maintenance, LLC (0.89%); Stripe-A-Zone, LLC (0.89%); Highway Traffic Control & Services, LLC (0.45%); Cold Creek Construction, LTD (0.73%); Fortson Contracting, INC. (1.08%); Bear Creek Construction, LLC (12.7%); Kdt Electric, LLC (0.26%); Professional Traffic Control LLC (0.16%); Murray Construction (0.64%); Jb Pinnacle Group, LLC (3.7%); Texas Environmental Management - San Antonio, INC. (1.51%); (Inactive)site Barricades (0.13%) |
| Progress | 95.68% complete, 106.11% of time used |
| Amount | $6,786,052 revised (original $6,535,505) |
| Change orders | $156,547 |
| Paid to date | $6,403,227 |
| Work | Hazard Elimination & Safety |
| Location | FM 2377, S. LOWRANCE RD to FM 983, Ellis County, Dallas District |
| Let / began | 2025-08-08 / 2025-11-03 |
| Latest estimate | 2026-10-05 |
| Contract number | 8253229 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.