# Knife River Corporation - South: TxDOT widen non-freeway contract 100%+ complete, FM 2818, Brazos County ($53,878,369, 27 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Knife River Corporation - South |
| Subcontractors | Green Teams, INC. (1.54%); Flasher Equipment Company (0.7%); Flovera Construction Services, LLC (2.82%); D & S Contracting, INC. (4.92%); Larry Young Paving, INC. (3.5%); M & D Foundation Drilling Industries, INC. (0.28%); Primate Construction, LP (0.02%); Texas Environmental Management - San Antonio, INC. (1.25%); Willow City Sign & Rail, INC. (0.77%); Scott Derr Painting Co, LLC (0.47%); Allstate Signal & Construction, LLC (5.96%); Area Wide Protective, INC. (0.12%); Brock Construction, LLC (0.26%); Cen Tex Hydroseed, INC. (0.41%); John Wright Construction (0.32%); Toro Bravo Construction, LLC (0.02%); Custom Fabricators & Repairs, INC. (0.15%); Batten Drilling, INC. (0.11%); Aggregate Technologies, INC. (0.03%); Farr Foundation, INC. (0.1%); Heatro Pipeline Services, L.L.C. (0.02%); Cedar Hill Services, LLC (0.02%); Aggieland Underground Excavations & More, LLC (0.05%); Chiron Communication Services, LLC (0.18%); 1 Priority Environmental Services, LLC (0.07%); Texas Cutting & Coring Gp, INC. (0.04%); Penhall Company (0.02%) |
| Progress | 102.13% complete, 103.73% of time used |
| Amount | $53,878,369 revised (original $45,254,645) |
| Change orders | $6,197,968 |
| Paid to date | $52,550,509 |
| Work | Widen Non-Freeway |
| Location | FM 2818, 0.5 MILES NORTH OF FM 60 to FM 2154, Brazos County, Bryan District |
| Let / began | 2020-09-04 / 2021-02-01 |
| Latest estimate | 2026-09-30 |
| Contract number | 9203203 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.