# Knife River Corporation - South: TxDOT rehabilitation of existing road contract 42% complete, FM 667, Ellis County ($9,679,717, 10 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Knife River Corporation - South |
| Subcontractors | USA Swppp Inspections, INC. (2.27%); Professional Traffic Control LLC (0.18%); Bear Creek Construction, LLC (11.34%); Stripe-A-Zone, LLC (0.82%); 4e Tree Worx LLC (0.62%); (Inactive)hogan Murray, INC. (0.73%); Dustin Allen, INC. (1.76%); Texas Traffic And Barricade, LLC (0.28%); (Inactive)site Barricades (0.28%); Site Partners, LLC (0.28%) |
| Progress | 41.74% complete, 65.66% of time used |
| Amount | $9,679,717 revised (original $9,501,431) |
| Change orders | $97,285 |
| Paid to date | $4,006,172 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 667, SH 34 to NAVARRO COUNTY LINE, Ellis County, Dallas District |
| Let / began | 2025-09-05 / 2025-11-17 |
| Latest estimate | 2026-10-05 |
| Contract number | 9253205 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.