# L A Fuller & Sons Construction, LTD.: TxDOT bridge replacement contract 27% complete, CS, Potter County ($2,000,761, 5 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | L A Fuller & Sons Construction, LTD. |
| Subcontractors | Wolfe Construction Group, Incorporated (0.34%); Emery Sapp & Son's INC. (0.43%); Trp Construction Group, LLC (0.67%); Carthage Drilling, LLC (2.95%); C & C Environmental Services (0.96%) |
| Progress | 26.92% complete, 33.77% of time used |
| Amount | $2,000,761 revised (original $1,996,761) |
| Paid to date | $537,502 |
| Work | Bridge Replacement |
| Location | CS, IRWIN RD @ EAST AMARILLO CREEK to ., Potter County, Amarillo District |
| Let / began | 2026-02-04 / 2026-07-13 |
| Latest estimate | 2026-10-06 |
| Contract number | 2263025 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.