# L A Fuller & Sons Construction, LTD.: TxDOT hazard elimination & safety contract 86% complete, SL 335, Randall County ($6,975,651, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | L A Fuller & Sons Construction, LTD. |
| Subcontractors | Urban Heights Investments LLC (0.21%); Dk Contracting, LLC (0.65%); Texas Environmental Management - San Antonio, INC. (0.65%); Trp Construction Group, LLC (1.59%); Professional Traffic Control LLC (0.18%); J. Lee Milligan, INC. (25.36%); Ci Construction & Landscape, LLC (0.34%) |
| Progress | 85.56% complete, 264.95% of time used |
| Amount | $6,975,651 revised (original $6,927,099) |
| Change orders | $40,552 |
| Paid to date | $5,961,761 |
| Work | Hazard Elimination & Safety |
| Location | SL 335, EASTERN ST to 0.65 MI EAST OF WHITAKER RD, Randall County, Amarillo District |
| Let / began | 2024-07-09 / 2025-01-06 |
| Latest estimate | 2026-10-06 |
| Contract number | 7243031 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.