# L & N Bridge, LLC: TxDOT bridge replacement contract 99% complete, FM 68, Fannin County ($2,926,144, 8 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | L & N Bridge, LLC |
| Subcontractors | Toro Bravo Construction, LLC (0%); Diamond Elite Barricades, LLC (0.54%); Elite Striping, LLC (0.34%); Wolfe Construction Group, Incorporated (0.53%); Hodges And Son Construction Company, INC. (8.82%); Peachtree Construction, LTD. (11.65%); Gary A. Crain, INC. (0.27%); Morris County Contractors, L.L.C. (1.33%) |
| Progress | 99.03% complete, 100% of time used |
| Amount | $2,926,144 revised (original $2,823,237) |
| Change orders | $16,330 |
| Paid to date | $2,812,138 |
| Work | Bridge Replacement |
| Location | FM 68, FM 68 AT NORTH SULPHUR RIVER, Fannin County, Paris District |
| Let / began | 2024-07-10 / 2024-12-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 7243228 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.