# Lakey, INC.: TxDOT widen non-freeway contract 98% complete, FM 697, Grayson County ($5,188,334, 8 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Lakey, INC. |
| Subcontractors | Dustin Allen, INC. (4.97%); C&J Contractors LLC (21.52%); Flex Supply, LLC (0.53%); Texop Construction (0.8%); Wopac Construction, INC. (7.36%); Stripe-A-Zone, LLC (2.83%); Drake Companies LLC (0.35%); Overland Corporation (0.16%) |
| Progress | 97.73% complete, 128.98% of time used |
| Amount | $5,188,334 revised (original $5,014,608) |
| Paid to date | $4,900,746 |
| Work | Widen Non-Freeway |
| Location | FM 697, FM 697 FROM MILL CREEK BRIDGE TO US 69, Grayson County, Paris District |
| Let / began | 2025-03-04 / 2025-07-21 |
| Latest estimate | 2026-10-05 |
| Contract number | 3253016 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.