# Lakey, INC.: TxDOT widen non-freeway contract 89% complete, FM 1131, Orange County ($5,104,462, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Lakey, INC. |
| Subcontractors | Trp Construction Group, LLC (2.34%); Texas Materials Group, INC. (26.06%); Cpave, INC. (0%); Surface Preparation Technologies, LLC (0.27%); American Remediation Options, INC. (3.77%); C&J Contractors LLC (12.17%); Cold Creek Construction, LTD (4.49%) |
| Progress | 89.17% complete, 121.31% of time used |
| Amount | $5,104,462 revised (original $5,072,329) |
| Change orders | $32,134 |
| Paid to date | $4,551,538 |
| Work | Widen Non-Freeway |
| Location | FM 1131, JASPER COUNTY LINE, SOUTH to FM 105 S, Orange County, Beaumont District |
| Let / began | 2025-03-04 / 2025-05-27 |
| Latest estimate | 2026-10-01 |
| Contract number | 3253021 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.