# Lakey, INC.: TxDOT bridge replacement contract 83% complete, CR, Jackson County ($1,949,129, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Lakey, INC. |
| Subcontractors | Flex Supply, LLC (1.2%); C&J Contractors LLC (57.55%); Carthage Drilling, LLC (9.66%); Sylva Construction, LLC (0%) |
| Progress | 83.04% complete, 144.89% of time used |
| Amount | $1,949,129 revised (original $1,929,627) |
| Paid to date | $1,602,314 |
| Work | Bridge Replacement |
| Location | CR, AT BRUSHY CREEK to STR# AA01-21-001 (BAGBY RD), Jackson County, Yoakum District |
| Let / began | 2025-03-05 / 2025-06-18 |
| Latest estimate | 2026-10-05 |
| Contract number | 3253223 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.