# Lamar Companies LLC: TxDOT interchange (new or reconstructed) contract 62% complete, US 69, Wood County ($39,060,728, 10 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Lamar Companies LLC |
| Subcontractors | Flex Supply, LLC (0.1%); Jb Pinnacle Group, LLC (1.54%); J. H. Oden Contracting Company (1.13%); Morris County Contractors, L.L.C. (0.44%); Striping Technology, L.P. (0.48%); Texop Construction (0.38%); True Roads, LLC (47.64%); M & D Foundation Drilling Industries, INC. (0.77%); Snowhill Contracting LLC (0.74%); Toro Bravo Construction, LLC (0.03%) |
| Progress | 62.42% complete, 91.76% of time used |
| Amount | $39,060,728 revised (original $37,954,683) |
| Change orders | $542,278 |
| Paid to date | $24,030,113 |
| Work | Interchange (New Or Reconstructed) |
| Location | US 69, 0.96 MI N OF FM 779, SE to 1.03 MI S OF FM 779, Wood County, Tyler District |
| Let / began | 2024-03-05 / 2024-05-13 |
| Latest estimate | 2026-10-02 |
| Contract number | 3243001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.