# Larry Young Paving, INC.: TxDOT bridge replacement contract 83% complete, US 79, Robertson County ($19,115,760, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Larry Young Paving, INC. |
| Subcontractors | Schneider Construction LLC (0.47%); Tor Texas, LLC (0.36%); Cen Tex Hydroseed, INC. (1.33%); Doran Steel, INC. (0.39%); Fc Traffic Control, INC. (0.24%); Highway 1 LLC (0.7%); Lindamood, INC. (0.94%); Penhall Company (0.14%); Professional Traffic Control LLC (0.02%); Statewide Materials Transport, LTD. (4.01%); Tom-Mac, INC. (4.04%); Willow City Sign & Rail, INC. (0.54%); Capital Pumping, LP (0.28%); Emery Sapp & Son's INC. (0.24%) |
| Progress | 83.49% complete, 88.61% of time used |
| Amount | $19,115,760 revised (original $18,997,916) |
| Paid to date | $15,860,697 |
| Work | Bridge Replacement |
| Location | US 79, AT LITTLE BRAZOS RIVER to ., Robertson County, Bryan District |
| Let / began | 2024-11-07 / 2025-02-13 |
| Latest estimate | 2026-09-30 |
| Contract number | 11243206 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.