# Larry Young Paving, INC.: TxDOT bridge replacement contract 15% complete, SH 105, Washington County ($2,898,512, 9 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Larry Young Paving, INC. |
| Subcontractors | Highway Traffic Control & Services, LLC (0.57%); Mar-Zap Construction, LLC (1.31%); Houston Sawing & Drilling (0.3%); Trp Construction Group, LLC (2.27%); Lifthigh Crane & Rigging, LLC (2.42%); Toro Bravo Construction, LLC (0.43%); Professional Traffic Control LLC (0.23%); Cen Tex Hydroseed, INC. (0.42%); Hodges And Son Construction Company, INC. (0%) |
| Progress | 14.72% complete, 12.73% of time used |
| Amount | $2,898,512 revised (original $2,813,308) |
| Paid to date | $414,097 |
| Work | Bridge Replacement |
| Location | SH 105, AT JACKSON CREEK to ., Washington County, Bryan District |
| Let / began | 2025-11-05 / 2026-04-06 |
| Latest estimate | 2026-09-29 |
| Contract number | 11253022 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.