# Larry Young Paving, INC.: TxDOT hazard elimination & safety contract 100%+ complete, US 79, Leon County ($3,092,438, 6 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Larry Young Paving, INC. |
| Subcontractors | Cen Tex Hydroseed, INC. (2.14%); Cen-Tree Solutions LLC (0.62%); D. I. J. Construction, INC. (4.66%); Highway Traffic Control & Services, LLC (1.57%); Memco Staffing, LLC (0.33%); Trp Construction Group, LLC (0.1%) |
| Progress | 104.86% complete, 100% of time used |
| Amount | $3,092,438 revised (original $2,870,625) |
| Change orders | $136,044 |
| Paid to date | $3,152,827 |
| Work | Hazard Elimination & Safety |
| Location | US 79, 0.1 MI E OF SH 75 to 0.2 MI E OF FM 1848, Leon County, Bryan District |
| Let / began | 2025-04-03 / 2025-08-04 |
| Latest estimate | 2026-09-29 |
| Contract number | 4253020 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.