# Larry Young Paving, INC.: TxDOT hazard elimination & safety contract 99% complete, SH 21, Brazos County ($7,077,676, 7 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Larry Young Paving, INC. |
| Subcontractors | Massana Construction INC. (1.58%); Trp Construction Group, LLC (2.51%); Cen Tex Hydroseed, INC. (0.6%); Klp Commercial, L.L.C. (11.51%); Professional Traffic Control LLC (0.35%); Traffic Signs & Lines, LLC (4.72%); Willow City Sign & Rail, INC. (1.63%) |
| Progress | 99.4% complete, 112.85% of time used |
| Amount | $7,077,676 revised (original $6,969,517) |
| Change orders | $11,309 |
| Paid to date | $6,938,879 |
| Work | Hazard Elimination & Safety |
| Location | SH 21, 0.3 MI W OF FM 50 S to BRAZOS COUNTY LINE, Brazos County, Bryan District |
| Let / began | 2024-07-10 / 2025-01-06 |
| Latest estimate | 2026-09-30 |
| Contract number | 7243212 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.