# Larry Young Paving, INC.: TxDOT hazard elimination & safety contract 57% complete, FM 974, Brazos County ($2,875,282, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Larry Young Paving, INC. |
| Subcontractors | Linear Traffic Markings LLC (1.32%); Cen Tex Hydroseed, INC. (2.1%); Willow City Sign & Rail, INC. (1.46%); Cen-Tree Solutions LLC (0.21%) |
| Progress | 56.73% complete, 73.89% of time used |
| Amount | $2,875,282 revised (original $2,808,685) |
| Change orders | $-10,824 |
| Paid to date | $1,587,280 |
| Work | Hazard Elimination & Safety |
| Location | FM 974, AT SH 6 WEST FRONTAGE RD. to ., Brazos County, Bryan District |
| Let / began | 2025-08-07 / 2026-01-05 |
| Latest estimate | 2026-09-29 |
| Contract number | 8253018 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.