# Lesna Construction, INC.: TxDOT rehabilitation of existing road contract 100%+ complete, RM 652, Culberson County ($24,168,204, 5 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Lesna Construction, INC. |
| Subcontractors | Pmi Pavement Marking, LLC (0%); Southeast Grinding And Grooving LLC (0.12%); Texacon Ep LLC (0%); Professional Traffic Control LLC (0.07%); Trp Construction Group, LLC (0.39%) |
| Progress | 100.68% complete, 106.39% of time used |
| Amount | $24,168,204 revised (original $22,966,171) |
| Change orders | $622,183 |
| Paid to date | $23,749,133 |
| Work | Rehabilitation Of Existing Road |
| Location | RM 652, 0.91 MI W OF FM 3541 to 4.08 MI E OF FM 3541, Culberson County, El Paso District |
| Let / began | 2023-11-01 / 2024-01-22 |
| Latest estimate | 2026-10-02 |
| Contract number | 11233005 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.