# Liberty Mutual Insurance Company: TxDOT rehabilitation of existing road contract 94% complete, FM 1495, Brazoria County ($8,777,058, 30 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Liberty Mutual Insurance Company |
| Subcontractors | M And J Construction Sawing (0.03%); Traffic Signs & Lines, LLC (0.18%); Inland Environments, LTD. (0.82%); Hass Co, LLC (0.3%); Master Curb, LLC (0.09%); Memco Staffing, LLC (4.03%); Hermanos Steel, LLC (0.79%); Hass Horizontal, LLC (0%); C.M. Nunez Trucking Company (0.73%); J.Kru Land Services, LLC (1.53%); Gmj Paving Company LLC (2.97%); Third Coast Services LLC (0.14%); Icon Gc, LLC (60.72%); Cherry Moving Company, INC. (1.27%); Trp Construction Group, LLC (1.89%); Smyrna Ready Mix Concrete, LLC (1.31%); (Inactive)c. M. Nunez Trucking, INC (0%); Hodges Brothers, INC. (0.1%); Southeast Grinding And Grooving LLC (0.6%); Texas Bro's Sawing And Sealing LLC (0.93%); Highway 1 LLC (2.29%); Sorrell Construction, Equipment & Materials, LLC (1.62%); Stripes & Stops Company, INC. (1.31%); Texas Environmental Control, INC. (0.2%); Double Oak Erosion, INC. (0.4%); Quality Turf Farms, L.C. (1.14%); Traf-Tex, INC. (0.07%); Dustrol, INC. (0.95%); Saw & Seal Of Texas LLC (1.64%); Conarmet LLC (1.55%) |
| Progress | 93.84% complete, 120.36% of time used |
| Amount | $8,777,058 revised (original $7,143,864) |
| Change orders | $1,533,163 |
| Paid to date | $8,142,626 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 1495, E BROAD ST to SH 36, Brazoria County, Houston District |
| Let / began | 2022-05-04 / 2023-02-06 |
| Latest estimate | 2026-09-30 |
| Contract number | 5223005 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.