# Longview Bridge And Road, LTD.: TxDOT bridge replacement contract 97% complete, US 271, Titus County ($22,992,908, 16 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Longview Bridge And Road, LTD. |
| Subcontractors | Innovative Roadway Solutions, LLC (0.11%); Cap River LLC (0.59%); Southwest Environment Services LLC (0.04%); Kiteco Property Solutions INC. (0.39%); Hx Farms, INC. (0.11%); Scout 5 Construction LLC (0.12%); Flex Supply, LLC (0.03%); Jb Pinnacle Group, LLC (0.43%); Emery Sapp & Son's INC. (0.16%); Toro Bravo Construction, LLC (0.03%); Hodges And Son Construction Company, INC. (0%); Isaacs Construction Services LLC (1.11%); Morris County Contractors, L.L.C. (1%); Panola Sign & Barricade, INC. (0.15%); Striping Technology, L.P. (0.72%); Farr Foundation, INC. (0.62%) |
| Progress | 97.22% complete, 95.14% of time used |
| Amount | $22,992,908 revised (original $22,227,359) |
| Change orders | $742,948 |
| Paid to date | $22,331,103 |
| Work | Bridge Replacement |
| Location | US 271, US 271 to AT DICKSON CREEK, BIG SLOUGH,, Titus County, Atlanta District |
| Let / began | 2021-11-04 / 2022-01-03 |
| Latest estimate | 2026-10-01 |
| Contract number | 11213228 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.