# Longview Bridge And Road, LTD.: TxDOT bridge replacement contract 23% complete, SH 64, Rusk County ($13,863,141, 10 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Longview Bridge And Road, LTD. |
| Subcontractors | Cap River LLC (1.02%); Southwest Environment Services LLC (1.28%); Kiteco Property Solutions INC. (0.69%); Flex Supply, LLC (0.15%); Morris County Contractors, L.L.C. (1.01%); Withers Construction, LLC (1.54%); Surface Preparation Technologies, LLC (0.1%); Toro Bravo Construction, LLC (0.28%); Striping Technology, L.P. (0.88%); Hodges And Son Construction Company, INC. (1.55%) |
| Progress | 23.44% complete, 27.94% of time used |
| Amount | $13,863,141 revised (original $13,629,478) |
| Change orders | $10,160 |
| Paid to date | $3,196,676 |
| Work | Bridge Replacement |
| Location | SH 64, CR 4133 to SL 571, Rusk County, Tyler District |
| Let / began | 2026-01-06 / 2026-05-08 |
| Latest estimate | 2026-10-02 |
| Contract number | 1263006 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.