# Longview Bridge And Road, LTD.: TxDOT bridge replacement contract 69% complete, SH 155, Marion County ($54,977,522, 12 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Longview Bridge And Road, LTD. |
| Subcontractors | J. H. Oden Contracting Company (0.47%); Emery Sapp & Son's INC. (0.12%); Snowhill Contracting LLC (1.51%); Striping Technology, L.P. (0.31%); Cap River LLC (0.21%); Hodges And Son Construction Company, INC. (3.62%); Isaacs Construction Services LLC (0.52%); Morris County Contractors, L.L.C. (0.38%); Panola Sign & Barricade, INC. (0.09%); Withers Construction, LLC (0.12%); West Texas Rock Resources, LLC (0.01%); Toro Bravo Construction, LLC (3.76%) |
| Progress | 69.1% complete, 75.45% of time used |
| Amount | $54,977,522 revised (original $53,799,919) |
| Change orders | $4,276,351 |
| Paid to date | $40,132,827 |
| Work | Bridge Replacement |
| Location | SH 155, SOUTH END OF BIG CYPRESS CREEK BRID to 1.5 MI W OF FM 729, Marion County, Atlanta District |
| Let / began | 2023-05-04 / 2023-06-28 |
| Latest estimate | 2026-10-02 |
| Contract number | 5233005 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.