# Longview Bridge And Road, LTD.: TxDOT convert non-freeway to freeway contract 90% complete, US 59, Angelina County ($63,840,014, 21 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Longview Bridge And Road, LTD. |
| Subcontractors | American Remediation Options, INC. (0.08%); Antigo Construction, INC. (0.04%); Hermanos Steel, LLC (5.45%); Morris County Contractors, L.L.C. (0.62%); Ancortex, INC. (2.24%); Buyers Barricades, INC. (0.13%); J. H. Oden Contracting Company (0.94%); John Wright Construction (1.04%); Moore Brothers Construction Company (8.38%); S & S Bridge Painting, INC. (0.02%); Striping Technology, L.P. (0.64%); West Texas Rock Resources, LLC (0.02%); Traf-Tex, INC. (0.71%); Hodges And Son Construction Company, INC. (1.99%); A&J Rebar LLC (0.08%); Texas Materials Group, INC. (8.38%); Kiteco Property Solutions INC. (0.07%); At Staffing (0%); Southeast Grinding And Grooving LLC (0.04%); Buyers Barricades Houston, LLC (0.13%); Ashton Sawing And Drilling LLC (0.03%) |
| Progress | 89.61% complete, 121.9% of time used |
| Amount | $63,840,014 revised (original $63,145,676) |
| Change orders | $516,838 |
| Paid to date | $57,051,114 |
| Work | Convert Non-Freeway To Freeway |
| Location | US 59, FM 2021 to .34 MILE NORTH OF SL 287, Angelina County, Lufkin District |
| Let / began | 2022-06-02 / 2022-09-14 |
| Latest estimate | 2026-10-05 |
| Contract number | 6223201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.