# Longview Bridge And Road, LTD.: TxDOT newlocation non-freeway contract 54% complete, IH 30, Bowie County ($71,360,119, 18 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Longview Bridge And Road, LTD. |
| Subcontractors | Cap River LLC (0.94%); Isaacs Construction Services LLC (0.5%); Toro Bravo Construction, LLC (1.57%); West Texas Rock Resources, LLC (0.01%); Hodges And Son Construction Company, INC. (1.1%); Morris County Contractors, L.L.C. (0.95%); S & S Bridge Painting, INC. (0.02%); (Inactive)statewide Safety Systems (0.33%); (Inactive)carthage Drilling, INC. (0.25%); Kiteco Property Solutions INC. (0.03%); Withers Construction, LLC (0.14%); C&J Contractors LLC (0.06%); Carthage Drilling, LLC (0%); Striping Technology, L.P. (0%); Farr Foundation, INC. (0.98%); Act Saw Cutting & Removal (0.09%); Emery Sapp & Son's INC. (0.01%); Jb Pinnacle Group, LLC (0.26%) |
| Progress | 54.35% complete, 80.77% of time used |
| Amount | $71,360,119 revised (original $58,800,540) |
| Change orders | $11,598,516 |
| Paid to date | $38,262,076 |
| Work | Newlocation Non-Freeway |
| Location | IH 30, FM 3419 to FM 989, Bowie County, Atlanta District |
| Let / began | 2022-06-02 / 2022-08-15 |
| Latest estimate | 2026-10-05 |
| Contract number | 6223202 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.