# Longview Bridge And Road, LTD.: TxDOT convert non-freeway to freeway contract 66% complete, SL 287, Angelina County ($11,280,207, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Longview Bridge And Road, LTD. |
| Subcontractors | A. L. Helmcamp, INC. (0.16%); Diamond Elite Barricades, LLC (0.26%); Kiteco Property Solutions INC. (0.82%); Texas Environmental Management - San Antonio, INC. (2.43%); Cold Creek Construction, LTD (0.59%); Striping Technology, L.P. (1.5%); Southwest Road & Safety Contractors, LTD. (1.16%); Third Coast Services LLC (4.55%) |
| Progress | 66.13% complete, 81.63% of time used |
| Amount | $11,280,207 revised (original $11,124,512) |
| Change orders | $63,758 |
| Paid to date | $7,398,583 |
| Work | Convert Non-Freeway To Freeway |
| Location | SL 287, BU 59G to COPELAND STREET, Angelina County, Lufkin District |
| Let / began | 2025-06-04 / 2025-09-08 |
| Latest estimate | 2026-10-05 |
| Contract number | 6253005 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.